Hydra Village Abu Dhabi - Construction Updates

Location: Al Shahama
Completion Forecast: Q4 - 2011
Development Type: villas

Hydra Village Abu Dhabi

Construction Milestone

Jan 14, 2010

Panoramic of view of Hydra Village Jan 2010

Hydra Village Abu Dhabi

Construction Milestone

Jan 14, 2010

Panoramic of view of Hydra Village Jan 2010

Hydra Village Abu Dhabi

Construction Milestone

Jan 11, 2010

1114 Villas in foundation stage -- 50 villas with structure 50% completed -- 94 villas with structure 100% completed -- 100 villas in finishing stage

Hydra Village Abu Dhabi

Construction Milestone

Jan 03, 2010

Zone 7: 296 villas in foundation stage + 47 villas structure 50% finished + 133 villas structure completed + 100 villas in finishing stage -- Other zones are in foundation stage --Zone 4: 79 villas -- Zone 6: 87 villas -- Zone 2: 103 villas --Zone8: 582

Hydra Village Abu Dhabi

Construction Milestone

Dec 07, 2009

Zone 7: 296 villas in foundation stage + 47 villas structure 50% finished + 133 villas structure completed + 100 villas in finishing stage -- Other zones are in foundation stage --Zone 4: 79 villas -- Zone 6: 87 villas -- Zone 2: 103 villas --Zone8: 582

Hydra Village Abu Dhabi

Construction Milestone

Nov 09, 2009

Project Status for Zone 7 and Zone 2 : 91 D3 villas in foundation stage + 128 C2 villas structure 50% + 100 C2 villas structure completed + 99 C2 villas in finishing stage + 6 Mock up villas completed - - Project Status Zone 6: + Trojan cast 15 PCC for th

Hydra Village Abu Dhabi

Construction Milestone

Oct 11, 2009

Enabling work completed in Zone 2, Construction Underway in Zone 7

Hydra Village Abu Dhabi

Construction Milestone

Sep 13, 2009

Enabling work completed in Zone 2, Construction Underway in Zone 7

Hydra Village Abu Dhabi

Construction Milestone

Aug 02, 2009

Enabling work completed in Zone 2, Construction underway in Zone 7

Hydra Village Abu Dhabi

Construction Milestone

Jul 06, 2009

Enabling work completed in Zone 2, Construction underway in Zone 7

Hydra Village Abu Dhabi

Construction Milestone

Jun 09, 2009

Enabling work completed in Zone 2, Construction underway in Zone 7.

Hydra Village Abu Dhabi

Construction Milestone

Apr 28, 2009

Concept Design Completed 100%, Enabling Work Completed in Zone 2 and Zone 7, Construction Underway in Zone 7

Hydra Village Abu Dhabi

Construction Milestone

Feb 25, 2009

Site work and Enabling works have begun in Zones 2 & 7