Hydra Avenue - Construction Updates

Location: Hydra Avenue is located on the waterfront of Reem Island, Abu Dhabi
Completion Forecast: Q4 - 2011
Development Type: Retail & Residential

Hydra Avenue

Construction Milestone

Jan 14, 2010

Hydra Avenue Jan 2010

Hydra Avenue

Construction Milestone

Jan 11, 2010

C6 transfer slab 100 % Completed -- C4 second typical floor slab 40 % Completed -- C5 first typical floor slab 100 % Completed

Hydra Avenue

Construction Milestone

Dec 07, 2009

C4 transfer slab casting completed -- C5 transfer slab 75 % completed -- C6 transfer slab 40 % completed

Hydra Avenue

Construction Milestone

Nov 09, 2009

UPC Approval for podium obtained - Enabling work 100% Completed - Pile cap 100% Completed - Raft slab 100% Completed

Hydra Avenue

Construction Milestone

Oct 11, 2009

Enabling work 100% Completed, Pile cap 100% Completed Raft slab 100% Completed, C4 Slabs: Basement Floor Slab Canal Side 100% Completed, Ground Floor Slab Canal Side 100% Completed, Podium First Floor Slab Canal Side 100% Completed, Columns: Podium Base

Hydra Avenue

Construction Milestone

Sep 13, 2009

Columns for basement for C4 & C5 100% Completed - Columns for basement for C6 , C7, C8 & C9 80% Completed - Columns for ground floor C4, C5, C6, C7 & C8 40% Completed - Columns for first floor for C4 40% Completed

Hydra Avenue

Construction Milestone

Aug 02, 2009

Columns for basement for C4 & C5 100% Completed - Columns for basement for C6 , C7, C8 & C9 80% Completed - Columns for ground floor C4, C5, C6, C7 & C8 40% Completed

Hydra Avenue

Construction Milestone

Jul 06, 2009

Columns for basement 85% Completed, Basement Slabs Commenced

Hydra Avenue

Construction Milestone

Jun 09, 2009

Piling 100% Completed, Main Contractor fully mobilized on site, Raft foundation complete, Columns for basement commenced.

Hydra Avenue

Construction Milestone

Apr 28, 2009

Temporary Site Work 100% Completed, Enabling Work Mobilization 100% Completed, Piling 100% Completed, Main Contractor fully mobilized on site, Raft foundation commenced

Hydra Avenue

Construction Milestone

Feb 25, 2009

Excavation of site has been completed. Building of foundations have begun and most of the columns have been driven into the ground to support the structure (63%)

Hydra Avenue

Construction Milestone

Feb 01, 2009

Construction Stages - Temporary site work 100% Enabling work mobilization 100%