Location: Business Bay, Dubai
Completion Forecast: Q4 - 2011
Development Type: Freehold commercial complex
Construction Milestone
Dec 07, 2009
PCW1: Form/Block work finished ,Blinding Concrete, Pile head treatment -- RAFT: Blinding Concrete, Pile head treatment (Water Proofing) --Tower Crane (s): Cast Foundations
Construction Milestone
Nov 09, 2009
Piling 100% completed - Main contractor fully mobilized on site - Zone 2 : Excavation and pile cut off +Concrete trail mix on going +Casting the blind concrete + Pile caps Block Work - Zone 3 : Excavation and pile cut off + Dewatering Hand over
Construction Milestone
Oct 11, 2009
Main contractor fully mobilized on site Zone 2: Excavation and pile cut off +Concrete trail mix on going +Casting the blind concrete +Pile caps Block Work Zone 3 : Excavation and pile cut off + Dewatering Hand over
Construction Milestone
Sep 13, 2009
Piling complete Main contractor fully mobilized on site , Zone 1 Excavation and pile cut off, Zone 2 Excavation and pile cut off, Concrete trail mix on going
Construction Milestone
Jul 06, 2009
Piling completed, Main contractor appointed and Mobilization commenced
Construction Milestone
Feb 25, 2009
Land stabilization and excavation fully completed. Preparing to enter construction stage of buildings foundations.
Construction Milestone
Feb 01, 2009
Tender stage building 100% Construction stages - Enabling work mobilization 100% Enabling work 91.16%