Location: City of Lights
Completion Forecast: Q4 - 2011
Development Type: Residential
Construction Milestone
Dec 07, 2009
Tower Raft Foundation Completed, Podium (B2) Slab & B1 Retaining Wall Completed, 3rd Floor to 4th Floor Columns & 4th Floor Slab in progress.
Construction Milestone
Nov 09, 2009
Construction Drawings 100% Completed - Building Approval obtained - Rebar & tendon installation 100% Completed - Column & Core wall erection from 1st to 2nd floor - Casting preparation for 2nd floor slab
Construction Milestone
Oct 11, 2009
Basement to ground columns and core walls casting completed, Retaining walls in progress,podium foundation raft in progress, ground floor slab for E1 in progress, tower columns & core walls in progress
Construction Milestone
Sep 20, 2009
Piling completed, Foundation Concreted and Waterproofed Concreting for retaining walls, basement columns and core walls in progress
Construction Milestone
Aug 02, 2009
Anti-termite application + Pile Heads treatment Completed - Foundations in progress
Construction Milestone
Jul 06, 2009
Piling 100% Completed, Main Contractor Mobilization Commenced, Anti-termite application + Pile Cap Binding + Tower Crane Erection in progress
Construction Milestone
Jun 09, 2009
Piling Work 100% Completed, Main Contractor Mobilization Commenced
Construction Milestone
Apr 28, 2009
Concept Design 100% Completed, Temporary site work 100% Completed, Enabling Work Mobilization 100% Completed, Enabling Work 100% Completed, Piling Work 100% Completed, Dewatering 100% Completed