Hydra 55 - Construction Updates

Location: City of Lights
Completion Forecast: Q4 - 2011
Development Type: Residential

Hydra 55

Construction Milestone

Jan 14, 2010

Hydra 55 Jan 2010

Hydra 55

Construction Milestone

Dec 07, 2009

Tower Raft Foundation Completed, Podium (B2) Slab & B1 Retaining Wall Completed, 3rd Floor to 4th Floor Columns & 4th Floor Slab in progress.

Hydra 55

Construction Milestone

Nov 09, 2009

Construction Drawings 100% Completed - Building Approval obtained - Rebar & tendon installation 100% Completed - Column & Core wall erection from 1st to 2nd floor - Casting preparation for 2nd floor slab

Hydra 55

Construction Milestone

Oct 11, 2009

Basement to ground columns and core walls casting completed, Retaining walls in progress,podium foundation raft in progress, ground floor slab for E1 in progress, tower columns & core walls in progress

Hydra 55

Construction Milestone

Sep 20, 2009

Piling completed, Foundation Concreted and Waterproofed Concreting for retaining walls, basement columns and core walls in progress

Hydra 55

Construction Milestone

Aug 02, 2009

Anti-termite application + Pile Heads treatment Completed - Foundations in progress

Hydra 55

Construction Milestone

Jul 06, 2009

Piling 100% Completed, Main Contractor Mobilization Commenced, Anti-termite application + Pile Cap Binding + Tower Crane Erection in progress

Hydra 55

Construction Milestone

Jun 09, 2009

Piling Work 100% Completed, Main Contractor Mobilization Commenced

Hydra 55

Construction Milestone

Apr 28, 2009

Concept Design 100% Completed, Temporary site work 100% Completed, Enabling Work Mobilization 100% Completed, Enabling Work 100% Completed, Piling Work 100% Completed, Dewatering 100% Completed

Hydra 55

Construction Milestone

Feb 25, 2009

Excavation works completed.