Hydra Downtown Tower - Construction Updates

Location: Burj Dubai
Completion Forecast: Q4 - 2011
Development Type: Retail & Offices

Hydra Downtown Tower

Construction Milestone

Nov 09, 2009

Piling Works 100% Completed

Hydra Downtown Tower

Construction Milestone

Oct 11, 2009

Piling Works 100% Completed

Hydra Downtown Tower

Construction Milestone

Jul 06, 2009

Piling Works 100% Completed

Hydra Downtown Tower

Construction Milestone

Jun 09, 2009

Piling Works 100% Completed

Hydra Downtown Tower

Construction Milestone

Feb 25, 2009

Ground surrounding construction site has been fully stabilized. Over 57% of land excavation complete. Piling in progress.

Hydra Downtown Tower

Construction Milestone

Feb 01, 2009

Construction stages - enabling work mobilization 100% Enabling work 100%