Location: Reem Island, Abu Dhabi
Completion Forecast: Q3 - 2011
Development Type: Retail, Residential, Offices
Construction Milestone
Jan 11, 2010
Formwork to 1st basement slab tower A Completed100% -- Rebar and post tensioning system to 1st basement slab tower A Completed 95% --Rebar & formwork to Water tank and core wall for Tower B Completed 90% -- Concrete casting to retaining walls up to 1st basement level Tower B Completed 70%.
Construction Milestone
Dec 07, 2009
Waterproofing to Pile caps and Main Raft for Tower A & B Completed, Rebar to Pile caps and Main Raft for Tower A & B on progress 90%, Concrete Pouring to Water Tank Foundation to Tower A & B Completed, Concrete casting to Columns & Retaining walls podium
Construction Milestone
Nov 09, 2009
2nd Tower crane erected 100% - 95% of basement raft completed and pour due to be completed by early next month
Construction Milestone
Oct 11, 2009
Tower crane erected 100%, Pile caps in progress as per schedule, Value engineering workshops progressing
Construction Milestone
Aug 02, 2009
Main Building Mobilization 100% Completed, Commencement of Pile Caps
Construction Milestone
Jul 06, 2009
Piling 100% Completed, Piling Excavation 100% Completed Main Build Mobilization 80% Completed
Construction Milestone
Jun 09, 2009
Piling Completed, Piling Excavation Completed, Main, Contractor appointed, Mobilization and Construction on site due to commence
Construction Milestone
Apr 28, 2009
Concept Design 100% Completed, Temporary Site Work 100% Completed, Enabling & Pilling Work 100% Completed, Pilling Excavation 100% Completed, Appointment of Main Contractor, mobilization and construction on site due to commence
Construction Milestone
Feb 25, 2009
Attained civil defense approval on site. 90% of pile excavation is complete.