Hydra Corporate Towers - Construction Updates

Location: Reem Island, Abu Dhabi
Completion Forecast: Q3 - 2011
Development Type: Retail, Residential, Offices

Hydra Corporate Towers

Construction Milestone

Jan 14, 2010

Hydra Corporate Towers Jan 2010

Hydra Corporate Towers

Construction Milestone

Jan 11, 2010

Formwork to 1st basement slab tower A Completed100% -- Rebar and post tensioning system to 1st basement slab tower A Completed 95% --Rebar & formwork to Water tank and core wall for Tower B Completed 90% -- Concrete casting to retaining walls up to 1st basement level Tower B Completed 70%.

Hydra Corporate Towers

Construction Milestone

Dec 07, 2009

Waterproofing to Pile caps and Main Raft for Tower A & B Completed, Rebar to Pile caps and Main Raft for Tower A & B on progress 90%, Concrete Pouring to Water Tank Foundation to Tower A & B Completed, Concrete casting to Columns & Retaining walls podium

Hydra Corporate Towers

Construction Milestone

Nov 09, 2009

2nd Tower crane erected 100% - 95% of basement raft completed and pour due to be completed by early next month

Hydra Corporate Towers

Construction Milestone

Oct 11, 2009

Tower crane erected 100%, Pile caps in progress as per schedule, Value engineering workshops progressing

Hydra Corporate Towers

Construction Milestone

Sep 13, 2009

Gunite works Completed, Appointment of sub contractor

Hydra Corporate Towers

Construction Milestone

Aug 02, 2009

Main Building Mobilization 100% Completed, Commencement of Pile Caps

Hydra Corporate Towers

Construction Milestone

Jul 06, 2009

Piling 100% Completed, Piling Excavation 100% Completed Main Build Mobilization 80% Completed

Hydra Corporate Towers

Construction Milestone

Jun 09, 2009

Piling Completed, Piling Excavation Completed, Main, Contractor appointed, Mobilization and Construction on site due to commence

Hydra Corporate Towers

Construction Milestone

Apr 28, 2009

Concept Design 100% Completed, Temporary Site Work 100% Completed, Enabling & Pilling Work 100% Completed, Pilling Excavation 100% Completed, Appointment of Main Contractor, mobilization and construction on site due to commence

Hydra Corporate Towers

Construction Milestone

Feb 25, 2009

Attained civil defense approval on site. 90% of pile excavation is complete.