Hydra Executive Towers - Construction Updates

Location: City of Lights
Completion Forecast: Q4 - 2011
Development Type: Commercial, Retail and Hotel Apartments

Hydra Executive Towers

Construction Milestone

Dec 07, 2009

Running of de-watering system, Piling is completed along with all snagging issues. Maintenance issues completed to de-water system, Tender analysis in progress

Hydra Executive Towers

Construction Milestone

Nov 09, 2009

Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence

Hydra Executive Towers

Construction Milestone

Oct 11, 2009

Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence

Hydra Executive Towers

Construction Milestone

Sep 13, 2009

Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence

Hydra Executive Towers

Construction Milestone

Aug 02, 2009

Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence

Hydra Executive Towers

Construction Milestone

Jul 06, 2009

Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence

Hydra Executive Towers

Construction Milestone

Jun 10, 2009

Piling 100% complete, Piling excavation in progress, Appointment of Main Contractor, Mobilization and Construction on site due to commence

Hydra Executive Towers

Construction Milestone

Feb 25, 2009

Excavation works completed. Ground surrounding construction site has be stabilized and piling mobilization has been completed.