Location: City of Lights
Completion Forecast: Q4 - 2011
Development Type: Commercial, Retail and Hotel Apartments
Construction Milestone
Dec 07, 2009
Running of de-watering system, Piling is completed along with all snagging issues. Maintenance issues completed to de-water system, Tender analysis in progress
Construction Milestone
Nov 09, 2009
Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence
Construction Milestone
Oct 11, 2009
Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence
Construction Milestone
Sep 13, 2009
Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence
Construction Milestone
Aug 02, 2009
Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence
Construction Milestone
Jul 06, 2009
Piling 100% Completed, Excavation Of Area 100% Completed, Appointment of Main Contractor, Mobilization and Construction on site due to commence
Construction Milestone
Jun 10, 2009
Piling 100% complete, Piling excavation in progress, Appointment of Main Contractor, Mobilization and Construction on site due to commence
Construction Milestone
Feb 25, 2009
Excavation works completed. Ground surrounding construction site has be stabilized and piling mobilization has been completed.