Marina Spirit - Construction Updates

Location: Marina Spirit towers is situated in the shoreline of City of Light marina, Al Reem Island, Abu Dhabi
Completion Forecast: Q4 - 2011
Development Type: Residential Usage

Marina Spirit

Construction Milestone

Feb 08, 2010

Marina Spirit Feb 2010

Marina Spirit

Construction Milestone

Jan 14, 2010

Site Progress: 5th Floor – 6th Floor Columns & 6th Floor Slab in progress.

Marina Spirit

Construction Milestone

Jan 13, 2010

Site Progress: Core Wall / Column & B2 Slab in progress, Tower Raft Foundation completed -- Tower 3B2a B2a-B1a Slab / Columns / Core Wall completed; B1a-LG Columns & Core Wall in progress --Tower 3B2b B3-B1 Slab / Core Wall completed; LG Slab in progress

Marina Spirit

Construction Milestone

Dec 07, 2009

Tower Raft Foundation Completed, Core Wall / Column & B2 Slab in progress

Marina Spirit

Construction Milestone

Nov 09, 2009

Temporary site work 100% Complete - Enabling work mobilization 100% Complete - Enabling work 100% Complete

Marina Spirit

Construction Milestone

Oct 11, 2009

Foundations commenced, Tower cranes have been erected

Marina Spirit

Construction Milestone

Aug 02, 2009

Foundations Commenced, Tower crane delivered on site

Marina Spirit

Construction Milestone

Jul 06, 2009

Piling 100% completed, Main contractor appointed and mobilized, Pile cap excavation 90% completed

Marina Spirit

Construction Milestone

Apr 28, 2009

Temporary Site Work 100% Completed, Enabling Work Mobilization 100% Completed, Enabling Work 100%Completed, Piling 95% Completed, Site mobilization and site survey being conducted by Main Contractor

Marina Spirit

Construction Milestone

Feb 25, 2009

Piling around site is completed. Excavation works 98% complete.

Marina Spirit

Construction Milestone

Feb 01, 2009

Construction Milestone Concept Design stage building - complete Construction stages temporary site work complete Enabling work mobilization complete